What is changing under the Control of Asbestos Regulations 2012?
From 25 November 2027, the contractor who carried out asbestos work can no longer appoint the person who assesses whether the area is suitable for reoccupation. The change comes through a new regulation 20 in the Control of Asbestos Regulations 2012 (CAR 2012). HSE says industry has a year to comply.
The change follows HSE's consultation on the regulations, which drew 358 responses. The amending regulations are The Control of Asbestos (Amendment etc.) Regulations 2026. They apply in England, Wales and Scotland. Asbestos has been banned since 1999, but it is still in many buildings, so the rules on how it is removed and cleared still matter to anyone managing a refurbishment or fit-out.
What is four-stage clearance?
When licensed asbestos removal finishes, the area cannot simply be handed back. HSE's HSG248 guidance for analysts sets out a four-stage clearance procedure. The stages are a preliminary check of site condition and job completeness, a thorough visual inspection inside the enclosure and work area, air monitoring inside the enclosure with disturbance of surfaces, and a final visual assessment of the work area after the enclosure has been dismantled.
If the area passes, the analyst issues the Certificate for Reoccupation, with signed copies going to the building owner or occupier and the licensed contractor. The certificate confirms the premises have been thoroughly cleaned and can be reoccupied.
What exactly changes under regulation 20?
The amending regulations substitute a new regulation 20 into CAR 2012. Under new regulation 20(3), anyone who appoints a person to assess whether the premises have been thoroughly cleaned and are suitable for reoccupation must ensure that person is accredited. New regulation 20(4) then adds a restriction:
"A person cannot be appointed to carry out an assessment under paragraph (3) by the employer who was required to ensure the premises or parts of premises were thoroughly cleaned in accordance with regulation 17(b)."
In practice, that is the asbestos removal contractor.
Until now the asbestos removal contractor has been allowed to appoint the assessor. The main change is that this stops. The explanatory note to the regulations confirms the asbestos removal contractor can still make the appointment before that date, and the change itself takes effect from 25 November 2027.
The requirement that the appointed person is accredited under ISO 17020 and ISO 17025 is already in the existing rules, and HSG248 refers to it.
Who will need to appoint the analyst?
The regulation says who cannot make the appointment. It does not name who must. In HSE's consultation, it is the client or dutyholder, such as the building owner or occupier, who appoints service providers.
HSG248 already strongly recommends that the analyst is employed by the building owner or occupier, to avoid conflicts of interest. For an owner or occupier who already follows that recommendation, the change will look familiar. For one who has left the appointment to the asbestos removal contractor, it means making the appointment themselves.
What else did HSE announce?
The press release covered more than the clearance change:
- Surveys: HSE continues to strongly recommend accredited organisations for asbestos surveys. This is a recommendation, not a legal requirement, and HSE plans further guidance and interventions.
- Notifiable non-licensed work: this category is being kept, with improved guidance to follow.
- Guidance: L143 and HSG248 are due to be updated later this year, along with new online guidance on appointing third-party providers.
HSE's asbestos pages are the place to check for those updates as they appear.
What does it mean for a fit-out or refurbishment project?
For a project in Guildford or central London that involves licensed asbestos removal, the practical effect is on who appoints whom. The building owner or occupier, or whoever manages the project for them, will need a route to an independent, accredited analyst that does not run through the asbestos removal contractor.
Projects that start now and finish before 25 November 2027 are still under the current arrangement. Projects running across that date, or starting after it, need the appointment planned from the outset. It also affects the order of work. The analyst needs to be in place before the removal finishes, so that the four stages of clearance are not held up waiting for an appointment.
Frequently asked questions
When do the new asbestos regulations come into force?
The change on who can appoint the analyst takes effect on 25 November 2027. The amending regulations as a whole come into force on 25 November 2026, according to the legislation itself. HSE's press release gives 24 November 2026, but the legal text is the authority. The current rules apply until the change takes effect, so an asbestos removal contractor can still appoint the analyst before 25 November 2027.
Who can no longer appoint the analyst?
The asbestos removal contractor. From 25 November 2027, the employer responsible for cleaning the premises after the work cannot appoint the person who carries out the assessment.
Is the analyst accreditation requirement new?
No. The requirement that the appointed person is accredited under ISO 17020 and ISO 17025 is already in the current regulation 20.
Are asbestos surveys now required to be carried out by accredited organisations?
No. HSE strongly recommends accredited organisations but has not made it a legal requirement.
PPT Health & Safety Consultants supports principal contractors and clients across Surrey, Hampshire and London with CDM support, Health & Safety advice and Site Inspections. If you would like to talk through a project or find out how we can help then get in touch.